12 hours ago, orion said:

it was sign and sealed that only a certain amount houses could be built at the start intill the stadium was built ...Was that kept to ? this is  about the 15th time in the last 4 years when we had so called positive news about moving forward and every time it never happens .

When it's  built then cheer but  intill then don't go over board about a company who  have never before   kept any promises or built any stadiums . I find it amazing there are  still people out there who think Osbourne clark and co will build it .

It seems your cautious approach may be correct. With Gaming International not bothering to attend you get a feeling they're wanting to sell all the land to the builders.

Link to comment
Share on other sites

If GamingUK is the stadium owner, and they've not exactly best buddies with the council by the sound of things, why would they want to crack on with the stadium? The carrot seems to be building more houses, but is there already a sufficient number built to enable them and the developers to now just sit back, do nothing, and start a dirty tricks strategy aimed at getting speedway kicked out altogether? This situation could just drag on for another few years

  • Like 2
Link to comment
Share on other sites

3 hours ago, greyhoundp said:

It would be interesting to know what this/these breaches are..

52
In 2015 the new s106 agreement agreed alongside the new 2015 outline planning
permission sought to further safeguard the delivery of the new stadium, amongst other
planning considerations and included the following requirements;
a)
To submit an application for reserved matters approval for the new stadium before
the defined "long stop date" and to use their reasonable endeavours to obtain planning
consent for the new stadium on or before the new stadium reserved matters planning
application long stop date; this was defined as 12 months after completion of the
agreement, namely before April 2016.
b)
That the applicant use "their reasonable endeavours to ensure and/or procure
Practical Completion of the New Stadium" on or before the defined stadium construction
"long stop date", defined as 18 months after the completion of the agreement in April 2015,
namely before October 2017.
c)
Not to occupy any additional residential units constructed on land identifie
d within the agreement (described as the "restricted zone" that is occupied by the existing stadium) until
the practical completion of the New Stadium.
d)
To make provision for a site for the Wiltshire Fire and Rescue Service (now the Dorset and Wiltshire
Fire and Rescue Service) for a new fire station north.
53
As described above at paragraph 15 above, although an application for reserved matters
approval for the new stadium was approved in August 2016, the works to carry out the
development did get underway and the new stadium was not completed in accordance with
the agreed "long stop date" of October 2017. The Borough Solicitor formally notified the
applicant and other parties with an interest in the land, that the failure to provide the open
space andto complete the new stadium was in breach of the s106 agreement.
Link to comment
Share on other sites

13 minutes ago, A ORLOV said:

Sounds like a foreign Delboy

I've said it before, and I'll say it again, never trust Clark Osborne. He was at Oxford and sold us down the river back in the middle seventies before the 'Save Oxford Speedway' and Greyhound people stepped in to save the stadium.

  • Like 2
Link to comment
Share on other sites

1 hour ago, cityrebel said:

You would have thought now that planning permission has been granted, they would have started work by now. If that wheelbarrow and kettle turn up, can someone please let us know.

Planning permission has been granted SUBJECT TO a number of conditions.

One of these is the completion of the section 106 agreement. So probably no track work until that has been signed off.

Link to comment
Share on other sites

8 hours ago, cityrebel said:

You would have thought now that planning permission has been granted, they would have started work by now. If that wheelbarrow and kettle turn up, can someone please let us know.

Tree has been cut down so no where plug in kettle. Workers used back straight bogs 3 weeks back not been seen since. Wheelbarrow being used by stadium to move new back straight grandstand.

  • Haha 2
Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.
Note: Your post will require moderator approval before it will be visible.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

×
×
  • Create New...

Important Information

We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue. Privacy Policy